Umon Island Solar Mini Grid Project: Third Mission Report to Umon Island
The installation of grid facility commenced in July and was completed in August. A total of 106 wooden electric poles were mounted across the two communities – Umon Island and Bagana Communities. Within the reporting period, some sensitization activities were carried out to encourage the community members to sign the end-users contract early and benefit […]